DataCenter Footprint: a digital common

This tool provides an estimation of the environmental footprint of a Data Center and the services it provides, combining models to enable a quicker evaluation and current reference methodologies including ADEME's Datacenters and Cloud Services PCR. Please refer to the documentation to know more.

Table of contents

A data center

Data center parameters

Data center environmental impacts, for 1 year of operation

Wondering about those acronyms ? See the documentation on the Datacenter lifecycle and environmental criterias.

For a data center of 5000m² in France with a lifespan of 30 years, with a Power Usage Effectiveness (PUE) of 1.45 and a load factor of 0.3, 5 MW of total power installed and 13140 MWh of total energy consumed in a year

Data center impacts per impact criterion, as absolute values, for 1 year of operation
Impact criterionManufacturingTransportUseEnd-of-lifeTotalUnit
Abiotic Depletion Potential Elements (ADPe)5.5111e+13.1605e-41.2395e+01.3646e-25.6365e+1kg Sb-Eq
Global Warming Potential (GWP)1.7251e+68.0447e+31.3880e+61.0155e+43.1313e+6kg CO2-Eq
Particulate Matter (PM)1.6207e-14.1406e-46.2262e-25.1810e-42.2527e-1disease incidence

⚠️ DCFootprint is in early stage. The methodology will be improved iterations after iterations. See the intended roadmap page to know what to expect next.

A server rack

Co-location / Housing (Functional Unit 1 in ADEME's PCR)

This represents the impacts of renting a rack, where the client of the datacenter is able to install and manage its physical IT equipments himself. It is based on the definition of the Functional Unit 1 in ADEME's Datacenters and Cloud services PCR methodology.

What ?Provide hosting services for operation of the IT equipment.
How much/many ?For 1 kW (one kilowatt) of commercialised IT power.
How long ?One year.

Functional unit results

Wondering about those acronyms ? See the documentation on the Datacenter lifecycle and environmental criterias.

For a data center of 5000m² in France with a lifespan of 30 years, with a Power Usage Effectiveness (PUE) of 1.45 and a load factor of 0.3, 5 MW of total power installed and 13140 MWh of total energy consumed in a year

These impacts are allocated according to Co-location / Housing (Functional Unit 1 in ADEME's PCR): provide hosting services for operation of the IT equipment, for 1 kW (one kilowatt) of commercialised IT power, for one year.

Totals for the functional unit per impact criterion, as absolute values, for 1 year of operation
Impact criterionManufacturingTransportUseEnd-of-lifeTotalUnit
Abiotic Depletion Potential Elements (ADPe)5.5111e+13.1605e-41.2395e+01.3646e-25.6365e+1kg Sb-Eq
Global Warming Potential (GWP)1.7251e+68.0447e+31.3880e+61.0155e+43.1313e+6kg CO2-Eq
Particulate Matter (PM)1.6207e-14.1406e-46.2262e-25.1810e-42.2527e-1disease incidence